02
Test levels of the virtual commissioning
| Level | What is tested | Numbers | State |
|---|---|---|---|
| Device | Each device is tested alone, and 113 also live against the PLC, with injected faults. | 186 devices. 960 of 960 checks. 1,937 of 1,937 PLC unit tests. | Done |
| Machine | Large machines are black boxes: real outer size, connections and signals, with simple behaviour. | 24 black-box machines. 7 stations specified at millimetre scale. | In progress |
| Area | Each area runs as a 3D scene against its own PLC program: step sequences, alarms and a fault test. | 10 areas, 10 area PLCs. 10 of 10 scenes built, 2 closed, 4 in test. More than 30 test windows so far. | In test |
| Plant | Areas will hand over by data records. Vehicles talk through a radio model, already tested. | 14 PLCs. Lost link: hold at 3 s, stop at 30 s. | Planned |